EF-2022-0155
Submission No.
Style of Case
In the Matter of the Application of Evergy Missouri West, Inc. d/b/a Evergy Missouri West for a Financing Order Authorizing the Financing of Extraordinary Storm Costs Through an Issuance of Securitized Utility Tariff Bonds
Events
Responsible Party | |||||
---|---|---|---|---|---|
12/6/2024 | Recommendation(s) |
|
Staff shall file a recommendation or status report about Evergy West’s proposed tariff sheets no later than December 6, 2024. | ||
12/6/2024 | Report(s) |
|
Staff shall file a recommendation or status report about Evergy West’s proposed tariff sheets no later than December 6, 2024. | ||
12/6/2024 | Comment(s) |
|
Any other comments about Evergy West’s tariff sheet shall be filed no later than December 6, 2024. | ||
2:00 PM to 4:00 PM |
2/2/2024
Conference (Hearing) |
|
Status Conference | WebEx Only | |
2:00 PM to 4:00 PM |
1/26/2024
Conference (Hearing) |
|
Status conference. Evergy Missouri West and Staff must appear at the status conferences, but other parties are not required to attend. | WebEx Only | |
12/29/2023 | Recommendation(s) |
|
Staff shall file its recommendation in this matter no later than December 29, 2023. | ||
12/29/2023 | Response(s) |
|
Any other responses to Evergy Missouri West’s tariff sheets shall be filed no later than December 29, 2023. | ||
11:00 AM to 1:00 PM |
12/5/2023
Conference (Hearing) |
|
The Commission will hold a status conference beginning December 5, 2023, at 11:00 a.m. Evergy and Staff must appear at the status conferences, but other parties are not required to attend. | WebEx Only | |
11/22/2023 | Statement(s) |
|
EMW must provide the Commission with an estimated timeline of its bond pre-issuance process...No later than November 22, 2023. | ||
11/22/2023 | Statement(s) |
|
Staff must inform the Commission whether Staff’s Finance Team has been able to participate and receive information during the pre-issuance process as ordered in Commission’s financing order, by 11/22. | ||
11/22/2023 | Statement(s) |
|
Staff must inform the Commission of any Staff concerns with the pre-issuance process no later than November 22, 2023. | ||
11/8/2023 | Response(s) |
|
Evergy Missouri West shall inform the Commission of the date it would need an order effective no later than November 8, 2023. | ||
11/8/2023 | Response(s) |
|
Any responses to Evergy Missouri West’s Motion for Nunc Pro Tunc Clarification and/or Correction shall be filed no later than November 8, 2023. | ||
10/4/2022 | Response(s) |
|
Staff Response | ||
9/30/2022 | Filing(s) |
|
Staff Filing | ||
9/30/2022 | Response(s) |
|
Any Other Responses | ||
9/12/2022 | Brief(s) |
|
Reply Briefs | ||
8/31/2022 | Brief(s) |
|
Initial Briefs | ||
8/10/2022 | Transcript(s) |
|
Transcript Filing Date | ||
9:00 AM to 5:00 PM |
8/1/2022 to 8/5/2022
Hearing (Hearing) |
|
Evidentiary Hearing | Room 310 | |
7/26/2022 | Discovery Deadline |
|
Last Day to Serve Discovery Requests | ||
7/26/2022 | Statement(s) |
|
Statements of Position | ||
7/25/2022 | List(s) |
|
List of Issues, List of Witnesses, Order of Cross-Exami | ||
7/22/2022 | Testimony |
|
Surrebuttal Testimony | ||
7/18/2022 | Conference (Hearing) |
|
Settlement Conference | ||
6/30/2022 | Testimony |
|
Rebuttal Testimony | ||
6/22/2022 | Response(s) |
|
Any Party's Response | ||
6/1/2022 | Data Request Response Time is 7 Calendar Days |
|
|||
5/2/2022 | Data Request Response Time is 10 Calendar Days |
|
|||
4/15/2022 | Procedural Schedule |
|
Proposed Procedural Schedule | ||
4/11/2022 | Procedural Schedule |
|
Joint Proposed Procedural Schedule | ||
4/4/2022 | Application(s) to Intervene |
|