Current Date/Time: 9/26/2025 3:07:47 PM
Calendar Display
EO-2012-0269
Submission No.
Style of Case
In the Matter of The Empire District Electric Company's Submission of Its Interim Report Regarding Participation in the Southwest Power Pool, Inc.
Events
Responsible Party | |||||
---|---|---|---|---|---|
9/1/2026 | Pleading |
|
Staff and OPC shall file a pleading concerning Liberty’s continued membership in SPP no later than September 1, 2026. | ||
8/14/2026 | Requested information |
|
Paragraph 2 of 09/25 Order Granting Interim Approval: Liberty shall provide the following information to OPC and Staff no later than August 14, 2026. | ||
9/17/2025 | Response(s) |
|
While no party is required to respond, responses or objections to the September 12, 2025 pleading filed by Staff and OPC shall be filed no later than September 17, 2025 | ||
9/12/2025 | Response(s) |
|
OPC and Staff shall respond to Liberty’s July 28, 2025 motion no later than September 12, 2025. | ||
8/20/2025 | Response(s) |
|
Any party wishing to respond to Liberty’s original motion for continuance of its SPP membership until all transmission facilities in the 2024 ITP are placed into service shall do so no by 8/20/25. | ||
8/11/2025 | Response(s) |
|
Any party wishing to respond shall do so no later than August 11, 2025. | ||
7/30/2025 | Objection(s) |
|
Any party objected to OPC’s motion shall do so no later than July 30, 2025. | ||
4/30/2024 | Response(s) |
|
Any party wishing to respond to the Motion for Continuation of Conditional Approval filed by Liberty on April 16, 2024, shall do so no later than April 30, 2024. | ||
7/20/2022 | Response(s) |
|
Any Party's Response to Motion | ||
4/30/2021 | Filing(s) |
|
Utility Filing | of 2021 Interim Report | |
2/24/2017 | Response(s) |
|
Response to Motion |