Current Date/Time: 5/21/2026 7:54:59 AM
Calendar Display
GC-2026-0278
GC-2026-0278
Submission No.
Style of Case
Latrell S. Germany, Complainant v. Spire Missouri, Inc. d/b/a Spire, Respondent
Events
| Responsible Party | |||||
|---|---|---|---|---|---|
| 5/25/2026 | Answer |
|
Spire shall file an answer to this complaint no later than May 25, 2026, and serve a copy upon the Complainant | ||
| 5/11/2026 | Explanation |
|
Complainant must clearly explain each violation by each utility no later than May 11, 2026 | ||
| 4/30/2026 | Clarifying Information |
|
No later than April 30, 2026, Complainant shall clarify the nature of her complaint with sufficient information for Respondents to answer the alleged violations and shall state the amount in dispute | ||
| 4/24/2026 | Pleading |
|
No later than April 24, 2026, Germany shall file a pleading clarifying whether he is acting on behalf of the Germany Family Trust or as a private individual and utility customer |