EO-2023-0407
Submission No.
EO-2023-0407
(Closed)
Style of Case
In the Matter of the Second Prudence Review of the Missouri Energy Efficiency Investment Act (MEEIA) Cycle 3 Energy Efficiency Programs of Evergy Metro, Inc. d/b/a Evergy Missouri Metro
Events
Responsible Party | |||||
---|---|---|---|---|---|
5/24/2024 | Response(s) |
|
No party is required to respond, but any responses to Staff’s Motion shall be filed on or before May 24, 2024. | ||
5/20/2024 | Discovery Deadline |
|
|||
5/17/2024 | Statement(s) |
|
Statements of Position | ||
5/7/2024 | Settlement Discussions |
|
|||
5/6/2024 | List(s) |
|
List of Issues, List and Order of Witnesses | ||
4/29/2024 | Testimony |
|
Surrebuttal Testimony Due | ||
3/29/2024 | Testimony |
|
Rebuttal Testimony Due | ||
3/29/2024 | Data Request Response Time is 10 Calendar Days |
|
Data Request (DR) Response time changes from 20 days to 10 days | ||
2/27/2024 | Testimony |
|
Direct Testimony Due | ||
2:00 PM to 4:00 PM |
12/6/2023
Conference (Hearing) |
|