GR-2022-0122
Submission No.
GR-2022-0122
(Closed)
Style of Case
In the Matter of Summit Natural Gas of Missouri, Inc.'s Changes to the Company's Purchase Gas Adjustment "PGA" Clause
Subject Company
Events
Responsible Party | |||||
---|---|---|---|---|---|
3/31/2024 | Production of Document(s) |
|
Company to Produce Information | ||
6/14/2023 | Filing(s) |
|
Settlement Agreement | ||
6/14/2023 | Procedural Schedule |
|
Joint Proposed Procedural Schedule | ||
5/15/2023 | Report(s) |
|
Status Report or Proposed Procedural Schedule | ||
4/10/2023 | Procedural Schedule |
|
Joint Proposed Procedural Schedule | ||
1/18/2023 | Response(s) |
|
Company Response | ||
8/22/2022 | Data Request Response Time is 20 Calendar Days |
|
|||
4:00 PM to 4:00 PM |
7/11/2022
Other |
|
|||
7/5/2022 | Statement(s) |
|
Statements of Position | ||
6/27/2022 | List(s) |
|
List of Issues, Order of Witnesses, Cross, and Opening | ||
6/22/2022 | Testimony |
|
Surrebuttal Testimony | ||
6/8/2022 | Testimony |
|
Rebuttal Testimony | ||
6/8/2022 | Data Request Response Time is 5 Calendar Days |
|
|||
5/13/2022 | Data Request Response Time is 10 Calendar Days |
|
|||
5/13/2022 | Testimony |
|
Direct Testimony | ||
12/1/2021 | Comment(s) |
|
Any Other Comments | ||
12/1/2021 | Procedural Schedule |
|
Proposed Procedural Schedule | ||
11/30/2021 | Recommendation(s) |
|
Staff Recommendation | ||
11/12/2021 | Recommendation(s) |
|
Staff Recommendation | ||
11/12/2021 | Recommendation(s) |
|
Any Comment on Tariff Sheet(s) or Staff Recommendation | ||
11/9/2021 | Recommendation(s) |
|
Staff Recommendation | ||
11/9/2021 | Response(s) |
|
Other Parties' Responses |