Current Date/Time: 5/13/2025 8:05:25 PM
Calendar Display
WA-2002-65
Submission No.
WA-2002-65
(Closed)
Style of Case
IN THE MATTER OF THE APPLICATION OF ENVIRONMENTAL UTILITIES, LLC FOR PERMISSION, APPROVAL, AND A CERTIFICATE OF CONVENIENCE AND NECESSITY AUTHORIZING IT TO CONSTRUCT, INSTALL, OWN, OPERATE, CONTROL, MANAGE AND MAINTAIN A WATER SYSTEM FOR THE PUBLIC LOCATED IN UNINCORPORATED PORTIONS OF CAMDEN COUNTY, MISSOURI (GOLDEN GLADE SUBDIVISION).
Subject Company
Events
Responsible Party | |||||
---|---|---|---|---|---|
3/12/2003 | Brief(s) |
|
Initial Brief | ||
3/12/2003 | Brief(s) |
|
Reply Brief | ||
3/12/2003 | Brief(s) |
|
Briefs | ||
8:30 AM to 5:00 PM |
2/19/2003
Hearing (Hearing) |
|
Governor Office Building, Room 310 | ||
8:30 AM to 11:00 PM |
2/19/2003
Hearing (Hearing) |
|
Jefferson City | ||
2/7/2003 | Testimony |
|
Parties' Rebuttal | ||
2/7/2003 | Testimony |
|
Rebuttal Testimony | ||
1/24/2003 | Testimony |
|
Direct Testimony | ||
1/24/2003 | Testimony |
|
Company Direct | ||
10/15/2002 | Procedural Schedule |
|
|||
10:00 AM to 5:00 PM |
10/9/2002
Conference (Hearing) |
|
Prehearing | Governor Office Building, Room 305 | |
10:00 AM to 10:00 AM |
10/7/2002
Conference (Hearing) |
|
Prehearing | ||
10:00 AM to 5:00 PM |
10/7/2002
Conference (Hearing) |
|
Prehearing | Governor Office Building | |
9/27/2002 | Conference (Hearing) |
|
Prehearing |