EA-2024-0292
Submission No.
Style of Case
In the Matter of the Application of Evergy Missouri West, Inc. d/b/a Evergy Missouri West for Permission and Approval of Certificates of Public Convenience and Necessity Authorizing It to Construct, Install, Own, Operate, Manage, Maintain and Control Two Solar Generation Facilities
Events
Responsible Party | |||||
---|---|---|---|---|---|
7/10/2025 | Brief(s) |
|
Reply Briefs | ||
6/27/2025 | Brief(s) |
|
Initial Briefs | ||
9:00 AM to 5:00 PM |
5/27/2025 to 5/28/2025
Hearing (Hearing) |
|
Evidentiary Hearing |
200 Madison Street Jefferson City, MO |
Room 310 |
9:00 AM to 11:00 AM |
5/22/2025
Conference (Hearing) |
|
Settlement Conference (location and time TBD) |
200 Madison Street Jefferson City, MO |
WebEx |
5/21/2025 | Statement(s) |
|
Position Statements | ||
5/20/2025 | List(s) |
|
List of Issues, Order of Witnesses, Order of Opening Statements, and Order of Cross Examination | ||
5/19/2025 | Testimony |
|
Surrebuttal | ||
5/19/2025 | Data Request Response Time is 5 Business Days |
|
|||
5/7/2025 | Testimony |
|
Rebuttal | ||
5/7/2025 to 5/19/2025 | Data Request Response Time is 10 Calendar Days |
|
|||
4/18/2025 | Response(s) |
|
OPC shall have until April 18, 2025, to file its response to Staff's Recommendation. | ||
4/17/2025 | Recommendation(s) |
|
No later than April 17, 2025, Staff shall file a recommendation regarding Evergy Missouri West’s application or a status report stating when it expects to file a recommendation. | ||
4/17/2025 | Report(s) |
|
No later than April 17, 2025, Staff shall file a recommendation regarding Evergy Missouri West’s application or a status report stating when it expects to file a recommendation. | ||
3/24/2025 | Response(s) |
|
No later than March 24, 2025, Staff shall file a response to Evergy Missouri West’s Response to Staff’s Motion for Extension and the Commission’s Sua Sponte Order Granting Staff’s Motion for Extension | ||
3/17/2025 | Recommendation(s) |
|
No later than March 17, 2025, Staff shall file a recommendation regarding Evergy Missouri West’s application or a status report stating when it expects to file a recommendation. | ||
3/17/2025 | Report(s) |
|
No later than March 17, 2025, Staff shall file a recommendation regarding Evergy Missouri West’s application or a status report stating when it expects to file a recommendation. | ||
12/16/2024 | Recommendation(s) |
|
Staff shall file a recommendation regarding the application, or a status report stating when it expects to file a recommendation, no later than December 16, 2024. | ||
12/16/2024 | Report(s) |
|
Staff shall file a recommendation regarding the application, or a status report stating when it expects to file a recommendation, no later than December 16, 2024. | ||
11/13/2024 | Application(s) to Intervene |
|
Applications to intervene in this matter shall be filed no later than November 13, 2024. |