EA-2025-0075
Submission No.
Style of Case
In the Matter of the Application of Evergy Missouri West, Inc. d/b/a Evergy Missouri West and Evergy Metro, Inc. d/b/a Evergy Missouri Metro for Permission and Approval of a Certificate of Public Convenience and Necessity for Natural Gas Electrical Production Facilities
Events
Responsible Party | |||||
---|---|---|---|---|---|
7/8/2025 | Brief(s) |
|
Reply Brief | ||
6/24/2025 | Brief(s) |
|
Initial Brief | ||
6/6/2025 | Transcript(s) |
|
The transcripts for the evidentiary hearing shall be expedited, with transcripts to be filed in EFIS no later than one week after hearing. | ||
9:00 AM to 5:00 PM |
5/28/2025 to 5/30/2025
Hearing (Hearing) |
|
Evidentiary Hearing |
200 Madison Street Jefferson City, MO |
Room 310 |
5/23/2025 | Discovery Deadline |
|
Discovery Cut-Off | ||
5/23/2025 | Statement(s) |
|
Position Statements | ||
9:00 AM to 5:00 PM |
5/22/2025
Conference (Hearing) |
|
Settlement Conference | TBD | |
5/21/2025 | Testimony |
|
Evergy Sur-Surrebuttal Testimony in Response to Additional Rebuttal to Evergy Supplemental Direct Testimony | ||
5/21/2025 | List(s) |
|
List of Issues, Order of Witnesses | ||
5/21/2025 to 5/23/2025 | Data Request Response Time is 5 Calendar Days |
|
The response time for DRs concerning Company’s Sur-Surrebuttal testimony shall be five calendar days to provide requested information, two calendar days to object or notify that more time is needed. | ||
5/14/2025 | Testimony |
|
Surrebuttal/Cross Rebuttal/Additional Rebuttal to Evergy Supplemental Direct Testimony | ||
4/26/2025 to 5/20/2025 | Data Request Response Time is 5 Business Days |
|
The response time for data requests shall be 5 business days to provide the requested information. | ||
4/25/2025 | Report(s) |
|
Staff Report | ||
4/25/2025 | Testimony |
|
Rebuttal and Intervenor Rebuttal | ||
12:00 PM to 4:00 PM |
4/1/2025
Hearing (Hearing) |
|
Local Public Hearing | WebEx Only | |
3/4/2025 | Objection(s) |
|
Any objections or comments on the notice language must be filed no later than March 4, 2025. | ||
3/4/2025 | Comment(s) |
|
Any objections or comments on the notice language must be filed no later than March 4, 2025. | ||
3/3/2025 | Filing(s) |
|
The parties shall jointly file proposed language/content for the local public hearing electronic publication notices no later than March 3, 2025. | ||
2/26/2025 to 4/25/2025 | Data Request Response Time is 10 Calendar Days |
|
The response time for all data requests shall be ten calendar days, and five calendar days to object or notify that more than ten calendar days will be needed to provide the requested information. | ||
2/19/2025 | Testimony |
|
Evergy Supplemental Direct | ||
2/13/2025 | Procedural Schedule |
|
Staff shall submit a new proposed procedural schedule no later than February 13, 2025. | ||
1/22/2025 | Procedural Schedule |
|
The joint motion for an extension is granted. The parties shall file a proposed procedural schedule in this matter no later than January 22, 2025 | ||
1/15/2025 | Procedural Schedule |
|
The Staff shall file a joint proposed procedural schedule on behalf of the parties no later than January 15, 2025. | ||
12/19/2024 | Application(s) to Intervene |
|
Any person or entity wishing to intervene shall file an application to intervene no later than December 19, 2024 | ||
12/3/2024 | Pleading |
|
The Commission’s Staff shall file a pleading stating a date certain that Staff can file a report about this CCN request |