In the Matter of the Application of Ameren Transmission Company of Illinois for a Certificate of Convenience and Necessity under Section 393.170.1, RSMo. relating to Transmission Investments in North Central Missouri
Subject Company
Events
Responsible Party | |||||
---|---|---|---|---|---|
4/2/2025 | Recommendation(s) |
|
No later than April 2, 2025, Staff shall file a recommendation on ATXI’s application or a request for additional time to file its recommendation. | ||
4/2/2025 | Procedural Schedule |
|
If the parties deem an evidentiary hearing appropriate, Staff shall collaborate with other parties and file a joint proposed procedural schedule, in lieu of recommendation by Staff, by April 2, 2025. | ||
1/27/2025 | Response(s) |
|
ATXI shall file a response to OPC’s Motion for a Commission Order to Make Information Public no later than January 27, 2025 | ||
1/27/2025 | Response(s) |
|
Any other responses to OPC’s Motion for a Commission Order to Make Information Public shall be filed no later than January 27, 2025 and may be filed by persons or entities not yet granted intervention | ||
1/20/2025 | Response(s) |
|
Responses to any applications to intervene shall be filed no later than January 20, 2025, and may be filed by persons or entities not yet granted intervention | ||
1/20/2025 | Response(s) |
|
Responses to MISO’s motion to submit direct testimony in support of the application shall be filed no later than January 20, 2025, and may be filed by persons or entities not yet granted intervention | ||
1/10/2025 | Application(s) to Intervene |
|
Any person or entity wishing to intervene in this matter shall file an application to intervene no later than January 10, 2025 |