Current Date/Time: 5/9/2025 5:06:18 PM
Calendar Display
EO-2025-0154
Submission No.
Style of Case
In the Matter of the Application of Evergy Metro, Inc. d/b/a Evergy Missouri Metro and Evergy Missouri West, Inc. d/b/a Evergy Missouri West for Approval of New and Modified Tariffs for Service to Large Load Customers
Events
Responsible Party | |||||
---|---|---|---|---|---|
5/6/2025 | Proposed hearing dates |
|
The Commission Orders all parties submit their proposed dates for a hearing from August 28, 2025 thru October 31, 2025 and those dates will be submitted no later than May 6, 2025. | ||
5/5/2025 | Procedural Schedule |
|
The Commission Orders all parties submit their Proposed Procedural Schedules no later than May 5, 2025. | ||
10:00 AM to 12:00 PM |
4/21/2025
Conference (Hearing) |
|
A prehearing conference shall be held by Web Ex for Staff Counsel and all parties on April 21, 2025 at 10:00 a.m. | WebEx Only | |
3/12/2025 | Response(s) |
|
The Staff of the Commission shall file a response to the proposed procedural schedule no later than March 12, 2025. | ||
3/12/2025 | Response(s) |
|
Any other responses to the proposed procedural schedule shall be filed no later than March 12, 2025. | ||
3/5/2025 | Application(s) to Intervene |
|
Any person or entity wishing to intervene shall file an application to intervene no later than March 5, 2025. |