Current Date/Time: 12/22/2024 1:17:11 PM
Calendar Display
EA-2022-0234
Submission No.
Style of Case
In the Matter of the Application of NextEra Energy Transmission Southwest, LLC for a Certificate of Public Convenience and Necessity to Construct, Install, Own, Operate, Maintain, and Otherwise Control and Manage a 345 kV Transmission Line and associated facilities in Barton and Jasper Counties, Missouri
Subject Company
Events
Responsible Party | |||||
---|---|---|---|---|---|
11/7/2022 | Filing(s) |
|
Settlement Agreement | ||
10/31/2022 | Report(s) |
|
Status Report | ||
10/21/2022 | Discovery Deadline |
|
Last Day to Issue Discovery | ||
10/14/2022 | Testimony |
|
Rebuttal Testimony | ||
10/6/2022 | Testimony |
|
Direct Testimony | ||
9/22/2022 | Recommendation(s) |
|
Staff Recommendation | ||
8/25/2022 | Recommendation(s) |
|
Staff Recommendation | ||
8/5/2022 | Application(s) to Intervene |
|