ER-2025-0348
Submission No.
Style of Case
In the Matter of the Application of Evergy Missouri West, Inc. d/b/a Evergy Missouri West for Authority to Implement Rate Adjustments Required by 20 CSR 4240-20.090(8) and the Company's Approved Fuel and Purchased Power Cost Recovery Mechanism
Events
Responsible Party | |||||
---|---|---|---|---|---|
8/8/2025 | Response(s) |
|
Any responses to Staff’s recommendation or comments on Evergy Missouri West’s tariff filing are due no later than August 8, 2025. | ||
7/30/2025 | Recommendation(s) |
|
Staff shall file a recommendation regarding its examination and analysis of Evergy Missouri West’s tariff filing no later than July 30, 2025. | ||
7/15/2025 | Application(s) to Intervene |
|