Current Date/Time: 5/20/2025 7:39:09 AM
Docket Sheet
WO-2005-0086
Status
Closed (8/19/2005)
Utility Type
Water
Type of Case
Other
Subject Companies
Style of Case
In the Matter of the Joint Application of Missouri-American Water Company and both Osage Water Company and Environmental Utilities, L.L.C. for Authority for Missouri-American Water Company to acquire the water and sewer assets of both entities, and for the transfer to Missouri-American Water Company of Certificates of Convenience and Necessity to continue operation of such assets as Water and Sewer Corporations regulated by the Missouri Public Service Commission
Assigned Judge
- Woodruff, Morris (Lead Judge)
Assigned Attorney
- Berlin, Bob (Lead Attorney)
Display Items:
-
Filter by Type of Filing:
Show Only:
or Hide:
Returning
94
/ 94
Filed on Behalf of | Response to Previous Filings | ||||
---|---|---|---|---|---|
94 |
8/18/2005
8:35 AM
|
Notice | Notice Closing Case | ||
93 |
7/14/2005
10:20 AM
|
Order | Order Denying Motion for Rehearing | ||
92 |
7/6/2005
2:23 PM
|
Order | Dissenting Opinion of Commissioners Steve Gaw and Robert M Clayton, III | ||
91 |
6/17/2005
2:59 PM
|
Motion | Motion for Rehearing, or, in this Case, to Actually Conduct a Hearing | 90 | |
90 |
6/9/2005
10:11 AM
|
Order | Order Dismissing Joint Application | ||
89 |
5/6/2005
12:34 PM
|
Other | Support of Intervener Hancock Construction for Staff Motion to Reject Transaction and Dismiss Application | ||
88 |
5/2/2005
3:36 PM
|
Motion | Motion to Reject Transaction and Dismiss Application | ||
87 |
3/16/2005
2:56 PM
|
Entry of Appearance | Entry of Appearance (Byrne) | 69 | |
86 |
3/14/2005
2:19 PM
|
Other | Response to Notice Concerning Cedar Glen Sewer | ||
85 |
3/11/2005
3:54 PM
|
Notice | Notice Regarding Staff Reply to Response of Osage Water Company to Staff`s Rate Analysis | ||
84 |
3/11/2005
3:16 PM
|
Response to Order | Response to Filings of the Staff | 78 , 79 , 82 | |
83 |
3/9/2005
11:53 AM
|
Notice | Notice Concerning Cedar Glen Sewer | ||
82 |
3/4/2005
2:38 PM
|
Other | Staff Reconciliation Relating to the Post-Sale Ratemaking Rate Base Value Attributable to Facilities Currently Owned/Leased/Used by Osage Water Company and Environmental Utilities | ||
81 |
3/3/2005
11:07 AM
|
Other | Response of Osage Water Company to Staff`s Ratemaking Analysis | ||
80 |
2/28/2005
9:27 AM
|
Order | Order Directing Response | ||
79 |
2/25/2005
2:21 PM
|
Response to Order | Supplemental Response to Order Adding Party and Directing Filing | ||
78 |
2/18/2005
5:03 PM
|
Response to Order | Response to Order Adding Party and Directing Filing | 69 | |
77 |
2/18/2005
3:13 PM
|
Response to Order | Position of the Office of the Public Counsel Regarding Whether a Need Exists to Increase Rates Customers Pay in Osage Water Company`s Service Territories | ||
76 |
2/10/2005
11:31 AM
|
Order | Order Regarding Clarification and Contempt | ||
75 |
2/4/2005
11:12 AM
|
Notice | Notice of Receipt of AmerenUE Permit | ||
74 |
2/4/2005
11:10 AM
|
Motion | Motion for Contempt Citation | ||
73 |
2/2/2005
4:31 PM
|
Small Company Rate Increase Request | Small Company Rate Increase Request | 69 | |
72 |
2/2/2005
11:01 AM
|
Notice | Notice of Receipt of AmerenUE Permit | ||
71 |
1/31/2005
9:12 AM
|
Joint Motion | Joint Motion for Clarification and Joint Motion to Shorten Time to Respond to Data Requests | ||
70 |
1/25/2005
1:42 PM
|
Ex Parte Notice | Notice of Ex Parte Contact (Commissioner Connie Murray) | ||
69 |
1/25/2005
11:02 AM
|
Order | Order Adding Party and Directing Filing | ||
68 |
1/20/2005
3:54 PM
|
Brief | Cedar Glen`s Pretrial Brief | ||
67 |
1/20/2005
1:35 PM
|
Request | Request of Intervener Hancock That Pretrial Brief Submitted on January 13, 2005, Be Consider the Pretrial Brief of Said Intervener | ||
66 |
1/20/2005
11:01 AM
|
Order | Order Canceling Hearing | ||
65 |
1/19/2005
6:04 PM
|
Statement of Position | MAWC`s Pretrial Brief | ||
64 |
1/19/2005
4:52 PM
|
Brief | Staff`s Pre-Trial Brief | ||
63 |
1/19/2005
4:02 PM
|
Brief | Pre-Hearing Brief of the Office of the Public Counsel | ||
62 |
1/19/2005
4:02 PM
|
Motion | Motion for Leave to File Pretrial Brief One Day Out of Time | ||
61 |
1/19/2005
3:28 PM
|
Other | Amended List and Order of Witnesses and Order of Cross-Examination | ||
60 |
1/19/2005
3:13 PM
|
Entry of Appearance | Entry of Appearance (Cooper, Williams, Comley, Allen, Duggan, O'Neill, Snodgrass) |
|
|
59 |
1/19/2005
3:04 PM
|
Other | List and Order of Witnesses and Order of Cross-Examination | ||
58 |
1/19/2005
3:02 PM
|
Transcripts | Transcript - Volume 3 (Prehearing Conference - Jefferson City, MO - January 14, 2005) | ||
57 |
1/19/2005
3:00 PM
|
Transcripts | Transcript - Volume 2 (Oral Argument - Jefferson City, MO - January 13, 2005) | ||
56 |
1/19/2005
1:51 PM
|
Motion | MAWC`s Motion for Continuance | ||
55 |
1/19/2005
1:00 PM
|
Brief | Pre-Trial Brief of Applicants Osage Water Company and Environmental Utilities, LLC | ||
54 |
1/19/2005
12:03 PM
|
Response To Motion | MAWC`s Response to Motion for Local Public Hearing | 52 | |
53 |
1/18/2005
5:00 PM
|
Motion | Notice of Non-Agreement as to List of Issues and Request for Brief Extension to File List of Witnesses | ||
52 |
1/14/2005
9:53 AM
|
Motion | Office of the Public Counsel`s Motion for Local Public Hearing and Request Not to Close Record Until After Testimony at the Local Public Hearing Has Been Received | ||
51 |
1/13/2005
2:07 PM
|
Brief | Brief of Intervener, Hancock on Legal Issues for Pretrial | ||
50 |
1/11/2005
12:21 PM
|
Other | Issues and Witnesses to be Presented by the Department of Natural Resources and Clean Water Commission at the Hearing | ||
49 |
1/7/2005
2:37 PM
|
Order | Order Granting Motion and Scheduling Argument | ||
48 |
1/7/2005
10:44 AM
|
Request | Request to Present Witness and Testimony on Certain Dates Due to Conflict | ||
47 |
1/7/2005
9:25 AM
|
Motion | Amended Motion for Extension of Time to File a List of Issues, List of Witnesses and Order/Cross of Witnesses | ||
46 |
1/6/2005
5:33 PM
|
Other | MAWC`s Proposed List of Issues | 35 | |
45 |
1/6/2005
5:05 PM
|
Other | Proposed List of Issues and Witnesses of the Staff of the Missouri Public Service Commission | ||
44 |
1/6/2005
3:48 PM
|
Other | Cedar Glen`s Separately Proposed Issue and List of Witnesses | ||
43 |
1/6/2005
2:30 PM
|
Motion | Motion for Extension of Time to File a List of Issues, List of Witnesses and Order/Cross of Witnesses | ||
42 |
1/6/2005
12:28 PM
|
Motion | Proposed List of Issues and Witnesses of the Office of the Public Counsel | ||
41 |
1/5/2005
10:47 AM
|
Other | List of Issues and Witnesses of Hancock Construction Company, Intervener | ||
40 |
12/30/2004
11:19 AM
|
Other | Answer of Department of Natural Resources and Clean Water Commission to Applicant Environmental Utilities` Request for Admissions | ||
39 |
12/30/2004
11:17 AM
|
Other | Supplemental Answers of Intervener Hancock to Requests for Admissions from Environmental Utilities | ||
38 |
12/29/2004
11:04 AM
|
Other | The Office of the Public Counsel`s Response Regarding and Objections to Environmental Utilities, L.L.C.`s Request for Admissions | ||
37 |
12/28/2004
11:16 AM
|
Other | Answer of Intervener Hancock to Requests for Admissions from Environmental Utilities | ||
36 |
12/28/2004
9:26 AM
|
Other | Response to Applicant Environmental Utilities, LLC`s Request for Admissions | ||
35 |
12/22/2004
7:52 AM
|
Order | Order Revising Procedural Schedule | ||
34 |
12/17/2004
12:04 PM
|
Request | Applicant Environmental Utilities, LLC`s Request for Admissions from Hancock Construction Company | ||
33 |
12/17/2004
12:02 PM
|
Request | Applicant Environmental Utilities, LLC`s Request for Admissions from Cedar Glen Condominium Owners Association, Inc. | ||
32 |
12/17/2004
11:59 AM
|
Request | Applicant Environmental Utilities, LLC`s Request for Aadmissions from Missouri Department of Natural Resources and Clean Water Commission | ||
31 |
12/17/2004
11:57 AM
|
Request | Applicant Environmental Utilities, LLC`s Request for Admissions from the Staff of the Missouri Public Service Commission | ||
30 |
12/17/2004
11:55 AM
|
Request | Applicant Environmental Utilities, LLC`s Request for Admissions from the Office of the Public Counsel | ||
29 |
12/14/2004
10:37 AM
|
Order | Order Establishing Procedural Schedule | ||
28 |
12/7/2004
10:54 AM
|
Application to Intervene | Application of Intervener Hancock Construction Requesting the it Receive the Entire Amount of Its Judgment Against the Sellers of the Assets to Missouri-American Water Company | ||
27 |
12/3/2004
4:07 PM
|
Entry of Appearance | Entry of Aappearance (Cooper, Williams, Angstead, Allen, Duggan, O'Neill, Snodgrass) | ||
26 |
12/3/2004
3:30 PM
|
Proposed Procedural Schedule | Jointly Proposed Procedural Schedule | ||
25 |
12/3/2004
2:26 PM
|
Transcripts | Transcript - Volume 1 (Prehearing - Jefferson City, MO - November 18, 2004) | ||
24 |
11/29/2004
11:01 AM
|
Other | Statement Concerning Staff Recommendation | 22 | |
23 |
11/23/2004
9:50 AM
|
Motion | Motion for Extension of Time to File a Proposed Procedural Schedule | ||
22 |
11/15/2004
5:09 PM
|
Staff Recommendation | Staff Recommendation | ||
21 |
11/15/2004
12:00 PM
|
Exhibit | Filing of Exhibits in Support of Claim | ||
20 |
11/12/2004
3:57 PM
|
Exhibit | Filing of Exhibits in Support of Claim | ||
19 |
11/10/2004
8:32 AM
|
Order | Order Granting Extension of Time | ||
18 |
11/9/2004
4:16 PM
|
Other | Cedar Glen Condominium Owners Association’s Certificate of Good Standing | ||
17 |
11/9/2004
12:48 PM
|
Motion | Motion for Additional Extension of Time to File Recommendation | ||
16 |
11/5/2004
7:48 AM
|
Order | Order Granting Intervention and Setting Prehearing Conference | ||
15 |
11/3/2004
4:08 PM
|
Application to Intervene | Application to Intervene | ||
14 |
11/2/2004
1:51 PM
|
Motion | Motion for Extension of Time to File Recommendation | ||
13 |
11/1/2004
2:07 PM
|
Application to Intervene | Application to Intervene | ||
12 |
10/20/2004
11:47 AM
|
Application to Intervene | Application of Hancock Construction Company to Intervene | ||
11 |
10/19/2004
8:20 AM
|
Order | Order Directing Notice, Setting Intervention Deadline, and Directing Staff Recommendation | ||
10 |
10/15/2004
11:02 AM
|
Response to Order | Supplement to Response to Commission Order | ||
9 |
10/13/2004
4:47 PM
|
Response to Order | Response to Commission Order | 4 | |
8 |
10/6/2004
4:52 PM
|
Other | Agreement D - Contract For Sale of Water System Assets and Sanitary Sewer System Assets of the Hurricane Deck Holding Company Being Operated Under the Regulatory Authority of the Osage Water Company to Missouri-American Water Company | ||
7 |
10/6/2004
4:43 PM
|
Other | Agreement C - Contract For Sale of Certain Sanitary Sewer System Assets Utilized By the Osage Water Company From Gregory D. Williams and Debra J. Williams to Missouri-American Water Company | ||
6 |
10/6/2004
4:38 PM
|
Other | Agreement B - Contract For Sale of Water Distribution System Assets of Environmental Utilities, L.L.C., to Misosuri-American Water Company | ||
5 |
10/6/2004
4:34 PM
|
Other | Agreement A- Contract for Sale of Water Distribution System Assets and Sanitary Sewer System Assets of the Osage Water Company to Missouri-American Water Company | ||
4 |
10/6/2004
11:28 AM
|
Order | Consolidated Primary Case | ||
3 |
10/5/2004
12:08 PM
|
Motion | Motion to Consolidate | ||
2 |
10/5/2004
12:04 PM
|
Motion | Motion for Protective Order | ||
1 |
10/5/2004
11:33 AM
|
Application | Joint Application and Motion for Expedited Treatment |