Current Date/Time: 9/24/2025 1:32:15 PM
Docket Sheet
ER-97-81
Status
Closed (9/18/1997)
Utility Type
Electric
Type of Case
Rate Case (Large)
Subject Companies
Style of Case
In the Matter of the Empire District Electric Company of Joplin, Missouri, for Authority to File Tariffs Increasing Rates for Electric Service Provided to Customers in the Missouri Service Area of the Company
Assigned Judge
Assigned Attorney
Related Submission No.
Consolidated To
Consolidated From
Data Request Contact Person
Display Items:
-
Filter by Type of Filing:
Show Only:
or Hide:
Returning
90
/ 90
Filed on Behalf of | Response to Previous Filings | ||||
---|---|---|---|---|---|
90 |
9/25/1997
|
Order | Order Granting Modification of Stipulation and Agreement | ||
89 |
9/19/1997
|
Motion | Motion to Modify Stipulation and Order on Behalf of Company | ||
88 |
9/18/1997
|
Order | Order Approving Tariffs in Compliance with a Commission Order | ||
87 |
9/17/1997
|
Staff Recommendation | Staff Recommendation | ||
86 |
9/15/1997
|
Tariff | Tariff (9800211) | ||
85 |
9/11/1997
|
Order | Order Approving Second Amendment to Unanimous Stipulation and Agreement | ||
84 |
9/2/1997
|
Other | Intervenor's Response to Empire's Second Amendment to the Stipulation and Agreement Letter | ||
83 |
8/28/1997
|
Stipulation and Agreement | Second Amendment to Unanimous Stipulation and Agreement (The Empire District Electric Company, Staff of PSC, Office of the Public Counsel, ICI Explosives USA, Inc., Praxair, Inc.) | ||
82 |
8/12/1997
|
Order | Order Regarding Motion for Rehearing | ||
81 |
8/1/1997
|
Other | Staff's Report on State Line Unit II | ||
80 |
7/31/1997
|
Motion | Office of the Public Counsel's Motion to Strike Notice | ||
79 |
7/30/1997
|
Transcripts | Transcript - Volume 3 (Hearing - Jefferson City, MO - July 10, 1997) | ||
78 |
7/28/1997
|
Notice | Notice on Behalf of the Empire District Electric Company | ||
77 |
7/25/1997
|
Application | Application for Rehearing on Behalf of the Empire District Electric Company | ||
76 |
7/24/1997
|
Order | Order Approving Tariffs in Compliance with Commission Order | ||
75 |
7/24/1997
|
Staff Recommendation | Staff Recommendation | ||
74 |
7/23/1997
|
Tariff | Substitute Sheet No. 5 | ||
73 |
7/21/1997
|
Tariff | Tariff | ||
72 |
7/16/1997
|
Order | Report and Order | ||
71 |
7/9/1997
|
Other | Staff's Verified Statement of Mark L. Oligschlaeger | ||
70 |
7/3/1997
|
Notice | Notice Setting Evidentiary Hearing | ||
69 |
7/1/1997
|
Other | Verified Statement of Robert B. Fancher on Behalf of the Empire District Electric Company | ||
68 |
6/30/1997
|
Other | Response to Notice on Behalf of the Office of the Public Counsel | ||
67 |
6/30/1997
|
Other | Response to Notice on Behalf of Empire District Electric Company | ||
66 |
6/30/1997
|
Status Report | Staff's In-Service Status Report on State Line Unit 2 (NP and HC) | ||
65 |
6/24/1997
|
Notice | Notice to Parties Regarding Ultimate Disposition | ||
64 |
6/23/1997
|
Other | Applicant's Waive Rights a Hearing, Letter | ||
63 |
6/23/1997
|
Other | First Amendment to Unanimous Stipulation and Agreement | ||
62 |
6/20/1997
|
Order | Order Establishing Motion to Modify the Order Establishing Test Year and Granting a Joint Motion for an Extension of Time | ||
61 |
6/19/1997
|
Notice | Joint Notice of Agreement in Principle | ||
60 |
6/16/1997
|
Other | Response to Joint Notice of Agreement in Principle and Joint Motion for Extension of Time | ||
59 |
6/13/1997
|
Brief | Staff's Brief on Payroll Expenses | ||
58 |
6/9/1997
|
Response | Response in Opposition to Motion to Modify Order Establishing Test Year on Behalf of the Office of he Public Counsel | ||
57 |
6/6/1997
|
Brief | Brief on Payroll Expenses on Behalf of the Office of the Public Counsel | ||
56 |
6/6/1997
|
Notice | Joint Notice of Agreement in Principle and Joint Motion for Extension of Time | ||
55 |
6/6/1997
|
Brief | Brief of the Empire District Electric Company Regarding True-Up Issue | ||
54 |
5/30/1997
|
Transcripts | Transcript - Volume 2 (Hearing - May 23, 1997) | ||
53 |
5/30/1997
|
Motion | Motion for Time to Reply to Motion to Modify Order Establishing Test Year on Behalf of the Office of the Public Counsel | ||
52 |
5/30/1997
|
Motion | Applicant's Motion to Modify Order Establishing Test Year | ||
51 |
5/23/1997
|
Notice | Notice Setting Due Date for Briefs | ||
50 |
5/23/1997
|
Entry of Appearance | Written Entry of Appearances | ||
49 |
5/22/1997
|
Testimony | Supplemental True-Up Testimony of David G. Winter (HC) | ||
48 |
5/22/1997
|
Testimony | Rebuttal Testimony (Fancher) on Behalf of the Empire District Electric Company | ||
47 |
5/15/1997
|
Exhibit | Staff's Late Filed Exhibit Number 34 | ||
46 |
5/13/1997
|
Order | Order Regarding Request for Rehearing Opening Docket, Providing Notice, and Granting Protective Order | ||
45 |
5/5/1997
|
Transcripts | Transcript - Volume 1 (Hearing - April 30, 1997) | ||
44 |
5/5/1997
|
Response | Staff's Response to Joint Request for Rehearing or Reconsideration | ||
43 |
5/2/1997
|
Testimony | Staff's True-Up Testimony (Winter) | ||
42 |
4/30/1997
|
Stipulation and Agreement | Stipulation and Agreement Presented Transcript Required | ||
41 |
4/23/1997
|
Request | Joint Request for Rehearing or Reconsideration of Portion of Commission "Notice" of April 18, 1997 | ||
40 |
4/18/1997
|
Notice | Notice Setting Presentation Time | ||
39 |
4/17/1997
|
Motion | Joint Motion for Hearing Schedule | ||
38 |
4/16/1997
|
Memorandum | Staff's Memorandum in Support of Stipulation and Agreement | ||
37 |
4/11/1997
|
Other | Applicant's Response to Requests for Hearing | ||
36 |
4/9/1997
|
Comments | Comments on Unanimous Stipulation Filed on Behalf of Stuart W. Conrad | ||
35 |
4/9/1997
|
Request | Staff's Request for Hearing | ||
34 |
4/9/1997
|
Request | Office of the Public Counsel's Request for Hearing | ||
33 |
4/4/1997
|
Stipulation and Agreement | Unanimous Stipulation and Agreement | ||
32 |
3/31/1997
|
Notice | Notice Issue Rescheduling Hearing Memorandum | ||
31 |
3/27/1997
|
Motion | Motion to Suspend the Filing of Hearing Memorandum and Case Reconciliation | ||
30 |
3/25/1997
|
Notice | Notice Issued Extending Filing of Hearing Memorandum | ||
29 |
3/24/1997
|
Motion | Motion to Reschedule Date for Hearing Memorandum and Reconciliation | ||
28 |
3/3/1997
|
Order | Order Regarding Intervention and Directing True-Up | ||
27 |
2/25/1997
|
Testimony | Exhibits to Johnstone Testimony Filed 2/20/97 | ||
26 |
2/20/1997
|
Testimony | Direct Testimony - Rate Design (Kind, Hall) on Behalf of Office of the Public Counsel | ||
25 |
2/20/1997
|
Testimony | Additional Direct Testimony of Donald E. Johnstone | ||
24 |
2/20/1997
|
Testimony | Staff's Direct Testimony (Beck, Christie, Mantle, PATTERSON, Pyatte, Ross, Watkins) | ||
23 |
2/20/1997
|
Testimony | Direct Testimony of John B. Lycan and David Meade | ||
22 |
2/13/1997
|
Testimony | Direct Testimony of BALDREE, Imhoff, BOLTZ, Winter, SCHWIETERMAN, Kiebel, FISCHER, MANTLE, CHRISTIE, PYATT, Warren, Patterson, Ahmad, Lin, Broadwater, Sochinski, Deering and Wood | ||
21 |
2/13/1997
|
Testimony | Direct Testimony of Donald E. Johnstone | ||
20 |
2/13/1997
|
Staff Recommendation | Staff's True-Up Recommendation | ||
19 |
2/13/1997
|
Testimony | Direct Testimony by Public Counsel (Burdette) | ||
18 |
12/13/1996
|
Order | Order Establishing Test Year and Directing True-Up | ||
17 |
12/13/1996
|
Notice | Correction Notice | ||
16 |
11/14/1996
|
Other | Response of the Empire District Electric Company to Staff's Test Year Recommendation | ||
15 |
11/13/1996
|
Order | Order Denying Application for Intervention and Establishing Procedural Schedule | ||
14 |
11/8/1996
|
Staff Recommendation | Staff's Test Year Recommendation | ||
13 |
11/8/1996
|
Other | Pleading Recommending Test Year Filed on Behalf of the Office of Public Counsel | ||
12 |
11/1/1996
|
Application to Intervene | Empire's Response in Opposition to Application for Intervention | ||
11 |
10/24/1996
|
Non-Disclosure Agreement | Non-Disclosure Agreement of Donald D. Johnstone | ||
10 |
10/23/1996
|
Application to Intervene | Application for Intervention on Behalf of Citizens Concerned for Children's Health | ||
9 |
10/23/1996
|
Proposed Procedural Schedule | Staff's Procedural Schedule Proposal | ||
8 |
10/11/1996
|
Testimony | Applicant's Direct Testimony (McKinney, Fancher, Gibson, Beecher, Murry and Brill) (Francher & Beecher (HC)) | ||
7 |
10/11/1996
|
Other | The Empire District Electric Company's Test Year Recommendation | ||
6 |
9/25/1996
|
Order | Order Granting Protective Order | ||
5 |
9/23/1996
|
Notice | Notice Issued Correcting Concurrences | ||
4 |
9/23/1996
|
Motion | Applicant's Motion for Protective Order | ||
3 |
9/20/1996
|
Order | Suspension Order and Notice | ||
2 |
9/10/1996
|
Application to Intervene | Application to Intervene Filed on Behalf of ICI Explosives USA, Inc. and Praxair, Inc. | ||
1 |
8/30/1996
|
Tariff | Empire District Electric Company's Tariff Revision Designed to Increase Rates, On a Permanent Basis, for Electric Service Provided to Customers in the Company's Missouri Service Area of the Company Tariff |