Current Date/Time: 11/21/2024 1:15:43 PM
Tariff
YE-2018-0105
Tariff Type
Revise Tariff
PSC MO No.
6
Current Status
Rejected (2/16/2019)
Issued Date
2/22/2018
Effective Date
2/16/2019
Related Submission No.
Purpose of Filing | Additional Information | ||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | 2/22/2018 | Revise Tariff |
The tariff sheets allow Ameren Missouri to implement its Charge Ahead – Electric Vehicles program, which will incentivize additional electric vehicle charging infrastructure development in the Ameren Missouri's service territory, which will encourage increased state-wide adoption of electric vehicle ownership to the benefit of Ameren Missouri's customers and the State of Missouri.
Tariff Sheet Details:
Original Sheet No. 165, Original Sheet No. 165.1, Original Sheet No. 165.2, Original Sheet No. 165.3, Original Sheet No. 165.4, Original Sheet No. 165.5, Original Sheet No. 165.6 |
Effective | 4/23/2018 | ||||||||||
Total: 1 file(s), 28.98 KB
|
|||||||||||||||
2 | 4/12/2018 11:40 AM | Commission Order | Order Suspending Tariffs and Directing a Prehearing Conference | Related Case Filing: | Suspended |
Suspended From
4/12/2018
Suspended Until 8/21/2018
|
|||||||||
Total: 1 file(s), 349.52 KB
|
|||||||||||||||
3 | 5/24/2018 11:17 AM | Commission Order | Order Setting Procedural Schedule And Further Suspending Tariffs | Related Case Filing: | Suspended |
Suspended From
5/24/2018
Suspended Until 2/21/2019
|
|||||||||
Total: 1 file(s), 302.17 KB
|
|||||||||||||||
4 | 2/6/2019 3:02 PM | Commission Order |
Report and Order
Reason for Rejection:
Other
Rejection Comments:
Per judge. See order. |
Related Case Filing: | Rejected | 2/16/2019 | |||||||||
Total: 2 file(s), 445.96 KB
|
JE-2013-0582 | 6 | Replace Tariff Entirely | Effective | 6/30/2013 |