EA-2026-0183
EA-2026-0183
Submission No.
Style of Case
In the Matter of the Application of Union Electric Company d/b/a Ameren Missouri for Permission and Approval and Certificates of Public Convenience and Necessity Authorizing it to Construct Renewable
Generation Facility and Battery Energy Storage Systems
Events
| Responsible Party | |||||
|---|---|---|---|---|---|
| 7/13/2026 | Recommendation(s) |
|
Staff shall file a recommendation regarding the application no later than July 13, 2026. | ||
| 6/29/2026 | Procedural Schedule |
|
At that conference the parties were directed to file a joint proposed procedural schedule no later than June 29, 2026. | ||
|
6/15/2026
1:00 PM to 3:00 PM |
Conference (Hearing) |
|
A prehearing conference will be held on June 15, 2026, beginning at 1:00 p.m., to be conducted via Cisco Webex telephone and video conference. |
200 Madison Street Jefferson City, MO |
WebEx |
| 6/12/2026 | Application(s) to Intervene |
|
Applications to intervene in this matter shall be filed no later than June 12, 2026. | ||
| 6/12/2026 | Response(s) |
|
Responses to the Motion for Protective Order shall be filed no later than June 12, 2026, and may be submitted by entities or persons not yet granted intervention |