Current Date/Time: 11/28/2026 12:44:49 AM
Calendar Display
EO-2027-0004
EO-2027-0004
Submission No.
Style of Case
In the Matter of the Application of Union Electric Company d/b/a Ameren Missouri for Approval of Decommissioning Cost Estimate for Callaway Energy Center and Funding Level of Nuclear Decommissioning Trust Fund
Events
| Responsible Party | |||||
|---|---|---|---|---|---|
|
12/3/2026
2:00 PM to 4:00 PM |
Conference (Hearing) |
|
The Commission will convene a procedural conference on December 3, 2026, at 2:00 p.m., via WebEx. | webex | |
| 10/30/2026 | Recommendation(s) |
|
The Staff of the Commission shall file its Recommendation or alternative pleading no later than October 30, 2026. | ||
| 10/5/2026 | Recommendation(s) |
|
The Staff of the Commission shall file its’ Recommendation or alternative pleading no later than October 5, 2026. |