Calendar Display
EO-2023-0448
Submission No.
Style of Case
In the Matter of the Application of Union Electric Company d/b/a Ameren Missouri for Approval of Decommissioning Cost Estimate for Callaway Energy and Funding Level of Nuclear Decommissioning Trust Fund
Events
Responsible Party | |||||
---|---|---|---|---|---|
3/13/2025 | Brief(s) |
|
Reply Briefs | ||
2/27/2025 | Brief(s) |
|
Initial Briefs | ||
9:00 AM to 5:00 PM |
2/6/2025
Hearing (Hearing) |
|
Evidentiary Hearing |
200 Madison Street Jefferson City, MO |
Room 310 |
1/30/2025 | Statement(s) |
|
Statements of Position | ||
1/23/2025 | List(s) |
|
List of Issues, Order of Opening Statements, Order of Witnesses, Order of Cross-Examination, etc. | ||
12/6/2024 | Testimony |
|
Surrebuttal/Cross-Surrebuttal | ||
11/8/2024 | Testimony |
|
Staff/OPC Rebuttal | ||
10/11/2024 | Testimony |
|
Ameren Missouri Direct | ||
9/10/2024 | Response(s) |
|
File Suggested hearing dates for January-March, 2025. | ||
9:00 AM to 11:00 AM |
7/12/2024
Conference (Hearing) |
|
The Commission will convene a procedural conference on July 12, 2024, at 9:00 a.m., via WebEx | WebEx | |
6/27/2024 | Response(s) |
|
The parties shall respond as ordered above no later than June 27, 2024. | ||
6/24/2024 | Response(s) |
|
The parties shall respond regarding a procedural schedule or alternative pleading no later than June 24, 2024 | ||
6/3/2024 | Recommendation(s) |
|
The Staff of the Commission shall file its Recommendation, or alternative pleading no later than June 3, 2024. | ||
6/3/2024 | Pleading |
|
The Staff of the Commission shall file its Recommendation, or alternative pleading no later than June 3, 2024. |