EA-2024-0212
Submission No.
Style of Case
In the Matter of the Application of Union Electric Company d/b/a Ameren Missouri for Permission and Approval and a Certificate of Public Convenience and Necessity
Events
Responsible Party | |||||
---|---|---|---|---|---|
10/16/2024 | Statement(s) |
|
Position Statements | ||
10/9/2024 | List(s) |
|
List of Issues, List of Witnesses, and Order of Cross-Examination Due | ||
8/29/2024 | Testimony |
|
Surrebuttal Testimony | ||
8/29/2024 | Discovery Deadline |
|
Last Day of Discovery | ||
9:00 AM to 5:00 PM |
8/5/2024
Conference (Hearing) |
|
Settlement Conference | TBD | |
7/30/2024 | Testimony |
|
Rebuttal Testimony Due (OPC, the Consumers Council of Missouri and Renew Missouri have the option of filing rebuttal testimony or surrebuttal testimony.) | ||
7/30/2024 | Data Request Response Time is 10 Calendar Days |
|
|||
7/19/2024 | Procedural Schedule |
|
No later than July 19, 2024, Staff, or another party, shall file a joint proposed procedural schedule on behalf of all parties or request an extension of time to do so. | ||
6/13/2024 | Application(s) to Intervene |
|
Applications to intervene in this matter shall be filed no later than June 13, 2024. |