Current Date/Time: 1/15/2025 2:40:52 AM
Docket Sheet
EO-2024-0251
Status
Closed (9/12/2024)
Utility Type
Electric
Type of Case
Change of Supplier
Subject Companies
Style of Case
In the Matter of the Application of Sullivan Development Properties, LLC for Change of Electric Supplier
Assigned Judge
- Walker, Karolin (Lead Judge)
Assigned Attorney
- Graham, Paul (Lead Attorney)
- Pringle, Travis
Related Submission No.
Consolidated To
Consolidated From
Data Request Contact Person
Kellogg, Kevin - Official Representative - Sullivan Development Properties, LLC (Other) (Other)
Display Items:
-
Filter by Type of Filing:
Show Only:
or Hide:
Returning
26
/ 26
Filed on Behalf of | Response to Previous Filings | ||||
---|---|---|---|---|---|
26 |
9/11/2024
1:56 PM
|
Order | Order Acknowledging Dismissal | ||
25 |
9/5/2024
4:50 PM
|
Notice | Notice of Voluntary Dismissal | ||
24 |
9/5/2024
4:40 PM
|
Response To Motion | Staff's Response to Joint Motion to Dismiss for Lack of Subject Matter Jurisdiction and Summary Determination | ||
23 |
8/26/2024
4:40 PM
|
Response to Order | Response to Order Directing Filing Granting Continuance | ||
22 |
8/26/2024
2:45 PM
|
Order | Order and Notice | ||
21 |
8/20/2024
3:06 PM
|
Motion | Ameren Missouri's and City of Farmington's Joint Motion to Dismiss for Lack of Subject Matter Jurisdiction and for Summary Determination | ||
20 |
8/16/2024
3:46 PM
|
Order | Order Directing Filing Granting Continuance | ||
19 |
8/6/2024
11:52 AM
|
Transcripts | Transcript - Volume 2 (Prehearing Conference - Jefferson City, MO via WebEx - August 5, 2024) | ||
18 |
7/22/2024
12:00 PM
|
Response to Order | City of Farmington Available Dates for Hearing | ||
17 |
7/22/2024
10:35 AM
|
Other | Ameren Missouri's Available Hearing Dates | ||
16 |
7/19/2024
4:47 PM
|
Other | Applicant's Available Dates | ||
15 |
7/19/2024
10:47 AM
|
Other | Staff's Available Hearing Dates | ||
14 |
7/17/2024
11:45 AM
|
Order | Order and Notice | ||
13 |
7/15/2024
5:20 PM
|
Response to Order | Applicant's Response to Order to Show Cause | 11 | |
12 |
7/12/2024
8:38 AM
|
Transcripts | Transcript - Volume 1 (Procedural Conference - Jefferson City, MO via WebEx - July 10, 2024) | ||
11 |
7/10/2024
4:40 PM
|
Order | Order to Show Cause | ||
10 |
7/1/2024
11:22 AM
|
Order | Order and Notice | ||
9 |
5/23/2024
8:30 AM
|
Status Report | Staff's Status Report and Recommendation | ||
8 |
5/22/2024
12:31 PM
|
Entry of Appearance | Entry of Appearance (Holthaus) | ||
7 |
5/3/2024
12:50 PM
|
Response To Motion | Ameren Missouri's Response to Application for Change of Electric Supplier | ||
6 |
5/3/2024
8:52 AM
|
Response to Order | Response of the City of Farmington, Missouri, to the Application of Sullivan Development Properties, LLC for Change of Electric Service Provider | 3 , 4 | |
5 |
5/3/2024
8:47 AM
|
Entry of Appearance | Entry of Appearance (Reid) | ||
4 |
4/3/2024
4:21 PM
|
Order | Order Directing Notice, Adding Parties, and Directing Responses to Application | ||
3 |
3/20/2024
3:21 PM
|
Application | Amended Application | ||
2 |
3/20/2024
1:56 PM
|
Notice | Notice of Deficiency | ||
1 |
3/18/2024
9:05 AM
|
Application | Application for Change of Electric Service Provider |